|  1 January 1945 The squad from "C" Company operated sand pit near Finsterthal. A
              shovel remained at work there also. All Companies were working
              hauling sand for controlling icy routes within Corps area as well
              as the secondary roads. Two trucks and a platoon from "B" Company
              completed a second task for the 7th Engrs. of hauling wire to town
              of Angelsberg. Two officers new in the Bn. were given their
              assignment. Lt. Baker was assigned as Asst. S-3, Lt. Huntington
              was placed with "C" Company.
 2 January 1945 In order to test-fire the Bn. 30 and 50 caliber machine guns a
              range was set up one-half mile west of Rollingen. Plans were afoot
              to fire each company's machine gun tomorrow. One platoon from each
              company was in reserve. The remainder of each company was
              committed to hauling sand for stock piling along hazardous
              stretches of Corps routes, both main and secondary.
 3 January 1945 The Bn's operations continued to be in general support of the XII
              Corps Engineer operation's efforts to control any hazardous road
              conditions continued. All companies hauled required sand for
              control of icy surfaces with one platoon from "B" Company in
              reserve. The sand pit was in continual operation by one squad of
              "C" Company. The Bn. machine guns were test fired by their ?? on
              1000 inch range in the vicinity of ??. During this season a
              creditable series of entertainment was arranged by Lt. Hubbard,
              Special Service officer.
 4 January 1945 No vital change took place within the Battalion operations.
              Hazardous road conditions prevailed throughout the assigned Corps
              road sector. This required constant patrolling and sanding which
              was done by two platoons from each company. Particular attention
              was paid to the routes along the higher ground where freezing
              conditions were more severe.
 5 January 1945 Conditions remained quite static. The major task remained the
              same, sanding and patrolling by each company of the dangerous icy
              spots on the assigned routes. Lt. Vose and Lt. Brakey received
              battlefield commissions and were assigned to "C" Company. With
              this addition of officer strength Lt. Villedsen and Lt. Snow
              returned to HQ. as Asst. S-2 Recon. officer.
 6 January 1945 A second shovel was place in pit near Finstorthal. All Bn's of
              Group were loading sand here. The Bn. continued working along the
              assigned corps MSR's and secondary roads. Two platoons from each
              company were committed to hauling sand and checking all icy
              points. Remaining platoons in reserve cleaned equipment.
 7 January 1945! Static conditions prevailed throughout all the companies. With the
              shovel working more efficiently through the day and night 180
              loads amounting to 450 yards. were produced at the pit. Some
              reconnaissance was being made at bridge sites along the Sauer
              River especially in the vicinity of Diekirch. This reconnaissance
              was performed during the night also.
 8 January 1945 Snow which continued to fall intermittently recovered the routes
              previously sanded. This required constant sanding. The routes
              commence on N-7 at Lintgen running North, Northeast and Northwest
              to the limits of the tactical situation. All companies had two
              platoons each controlling the hazardous road surfaces. Security
              was also emphasized. Several homes of known enemy sympathizers in
              Rollingen were visited and investigated by S-2. Lofts of housing
              carrier pigeons were also searched for.
 9 January 1945 Each company was employed in snow removal using blade mount on 4
              Ton truck. The reserve platoon in each company conducted a 3-hour
              refresher course in Infantry tactics. Plans for the experimental
              use of salt and sand mixture for ice control were affected. "A"
              and "B" Company's sent a platoon each to the ?? Engrs. and 166
              Engrs areas respectively to familiarize themselves with the named
              Bn's barrier plan.
 10 January 1945 No improvement in road conditions and the persistent accompanying
              hazards was noted. Therefore each company continued minus one
              platoon in the routine work of constantly sanding the assigned
              routes.
 11 January 1945 Infantry tactics were being reviewed further in each company. A
              bill of materials for the eventual barge and boom construction was
              being drawn up by Lt. Baker according to specified instructions. A
              visit was paid by Lt. Lyon, former Bn. Adjutant now with Group, to
              S-2 and 3.
 12 January 1945 Routine operations remained unchanged throughout the Bn. Our
              assignment of maintaining routes, both main and secondary in a
              sector of Corps area, was fulfilled by two platoons from each
              Company. These platoons hauled sand and patrolled icy hazardous
              points. The three remaining platoons of each company cleaned and
              did maintenance work on their equipment. An experiment of
              spreading a mixture of 10% salt with sand was conducted on icy
              roads. This percentage of salt was found to be too great and was
              reduced. This proved satisfactory for dissolving and ice
              conditions creating a road hazard.
 13 January 1945 No change in duties were received. However, a new area divided
              into 3 zones was assigned to Bn. south and west of city of
              Luxembourg. Two reconnaissance parties were despatched to find
              requirements and possibilities for creating a barrier here. The
              Bn. procured a dozer. This was mounted on a Sherman 27-Ton medium
              tank. One enlisted man from each company was selected for driving
              and maintenance instructions on this piece of equipment.
 14 January 1945 With the tank-dozer now within the Bn., high interest was shown in
              its operative features. Its blade operated hydraulically. Capacity
              production was being maintained at the sand pit operated by a
              squad from "C" Company. The usual quote of two platoons continued
              work along all routes of hazard.
 15 January 1945 A trial inflation was made by one platoon from "A" Company of
              Pneumatic boats and loading on vehicles with the saddles was
              conducted at 509th LP Co. Control of road hazards due to frozen
              snow and ice continued to be SOP. Awards within the Bns. were
              presented at ceremonies held in Mersch theater. One of the more
              notable features was the unexpected yet deserved award of the
              D.S.C. to Lt. Col. Reagan. All awards including Bronze and Silver
              Stars were personally presented by XII Corps Commander, Major
              General Eddy.
 16 January 1945 The sand pit produced 149 loads totaling 285 yards. One squad from
              "C" Company was operating the pit. One platoon from "A" and "B"
              Company were each occupied cleaning and maintaining their
              equipment.. The balance of all companies were active in the
              routine operations of ice control.
 17 January 1945 Operations were developing and of a more interesting nature in the
              Bn. area. One platoon from "A" Company prepared and assembled
              equipment to construct Treadway Bridge in the vicinity of
              Gilsdorf. This was also true of "B" Company whose materials were
              being assembled for construction of Treadway in the vicinity of
              Diekirch. "C" Company completed Bailey Bridge, 80' D/S at
              Ettelbruck. Control of all hazardous road areas caused by snow or
              ice was still continued as an important Bn. mission.
 18 January 1945 All companies were at work on bridges with varying success. "C"
              Company completed a second 80' D/S Bailey Bridge North of
              Ettelbruck uninterrupted despite sporadic artillery fire in the
              vicinity. "A" Company worked at Gilsdorf with progress more slow.
              After evaluating the situation a decision to commence work was
              made at 1200 hours. However, nothing could be accomplished until
              1400 hours and then was terminated by an immediate mortar barrage.
              Resumption started at 1840 hours. The Treadway Bridge over the
              river near Diekirch could not be placed. Mines and booby traps
              plus the tactical situation made work impractical. Plans to
              commence as soon as feasible. With these missions done, injuries
              were counted up. It was found that Lt. Gray was lightly hurt. Also
              four from "A" Company.
 19 January 1945 "A" Company, having finished their floating Treadway at Giladorf,
              placed an anti-mine beam 300 yards west of the bridge. One platoon
              worked on the approaches and maintained same while another
              provided security here. While standing by to build a Class 40
              Heavy Pontoon Bridge at Diekirch "B" Company cleared mines and
              obstacles on roadway leading to bridge site. "C" Company placed
              Treads on both Bailey Bridges at Ettelbruck. Two squads provided
              security for these bridges. A road to bridge located Northeast of
              Ettelbruck was also constructed. Promptness in Treading Baileys
              was very necessary now due to the substantial peril the chess
              created by tanks now using snow and grousers on there treads.
 20 January 1945 "A" and "C" Companies worked on placing two Bailey Bridges
              Northeast of Ettelbruck. The first named Bridges finished 120' D/D
              over RR with a continuing Ramp to "C" Company T/S Bailey Bridge of
              90' over the Sauer River. Treading was placed by midnight. The
              task of "B" Company at Diekrich was completed at 1050 hours. This
              160' Heavy Pontoon erection had been substantially delayed due to
              enemy placed mines. Also the time was consumed awaiting an
              additional heavy Pontoon required beyond previous position caused
              this addition. Final Treading was put on by 1430 hours.
 21 January 1945 "A" Company was well occupied disposing of minefield in the
              vicinity of their bridge site. Total destroyed was 642 Schu mines.
              18 Tellermines (No. ?) and 9 U.S. anti-tank mines. One squad from
              "B" Company was placed to operate sand pit west of Mersch. "C"
              Company maintained three Bailey Bridges with one platoon which
              were previously constructed by the company. One squad also worked
              removing minefields near Ettelbruck.
 22 January 1945 "B" Company oriented two platoons in the rear barrier zone of 5th
              Division. A minefield was cleared by one platoon from "C" Company
              at bridges where a second platoon did maintenance work in the
              vicinity of Ettalbruck. "A" Company was mainly occupied sanding
              hills and curves along MSR's. Two platoons where used.
 23 January 1945 "A" Company had three platoons occupied all the day. Two were
              working on a 120' D/D Bailey Bridge, South of Lipperscheid. It was
              now not the site but the steep hair-pin turn road leading to it
              which presented problems for vehicles bearing construction
              material. This delayed a rapid conclusion of the task. The barrier
              zone in 5th Division rear area, manned by two platoons from "B"
              Company. "C" Company besides its maintenance work on bridges North
              of Ettelbruck a platoon on more sanded roads.
 24 January 1945 "A" Company retained one squad to maintain the D/D 120' Bailey
              Bridge which was finished just south of Lipperscheid at noon. "B"
              company in addition to squat operating sand pit, placed 2 platoons
              on a 4-hr alert to non Barrier zone. The adjoining Bailey Bridge
              in Ettelbruck were under constant maintenance by a "C" Company
              squad. All companies had men removing snow and sanding roads. The
              routes followed the Rippweiler Northeast thru Boevange and Bissen
              to Colmar and Ettelbruck. Also main route from Luxembourg North to
              Mersch with secondary roads containing hazards which are located
              between these main supply routes.
 25 January 1945 A squad from "A" Company cleared debris from road at bridge site
              South of Lipperscheid. A second squad maintained bridge at first
              named site. "B" Company continued operation of the Sand Pit and
              had two platoons on four hour alert to man 5th Division rear area
              barrier zone. The bridges were still on "C" Companies work
              assignment for maintenance North of Ettelbruck. Roads requiring
              sanding, plowing, or any other work to hazards were attended to by
              each company in its sector.
 26 January 1945 Reconnaissance has been quite extensive in an effort to find a
              suitable grade and location of a sand or gravel pit. A 140' T/S
              Bailey Bridge was placed over the RR and Sauer River about one
              mile north of Bourscheid. Construction started at 1415 hours and
              at 2030 hours it was completed. This mission was a "C" Company
              accomplishment with 2 platoons. Besides a fairly complete coverage
              of all more traveled routes which were being plowed of snow and
              sanded by all companies. "A" Company kept its Bailey Bridge South
              of Lipperscheid in working order. "B" Company with one squad
              supplied sand from pit west of Mersch and was ready to man barrier
              zone on a 4-hour notice. "C" Company maintained their bridges at
              Ettelbruck.
 27 January 1945 Plans for a coordinated move of HQ in an exchange of location with
              133rd Engr. was arranged to take place in the morning. A 110' T/S
              Bailey Bridge was 15% complete at 1800 hours with plans to resume
              work on it tomorrow. Two platoons were on this task. The road from
              Bourscheid to a point 5 miles north was being swept and cleared of
              mines by a "C" company platoon. Also an airstrip at Ettelbruck was
              cleared of snow by &laqo; squad from the same company. At 2050
              hours a 140' T/S Bailey Bridge was completed by two platoons from
              "C" Company located at ?? South of Schlindermanderscheid. The
              routine but vital tasks of keeping roads cleared from snow and ice
              continues with all companies.
 28 January 1945 Bn.. HQ. with H&S Company established new operational quarters
              in the morning at Colmar. "C" Company also found quarters with its
              CP here. "A" Company relocated in Berg. With one air strip cleared
              of snow by "C" Company yesterday the D-7 was dispatched from "A"
              Company to remove snow from a second strip between Bissen and
              Colmar. Two platoons were also occupied placing a Bailey Bridge of
              110' Length T/S on Sauer River slightly North of previous "C"
              Company Bailey Bridge. Besides working Sand Pit and remaining as
              yet on 4 hour alert to man barrier zone "B" Company as did all the
              other companies patrolled, sanded, and plowed all their vital
              routes. Slippery conditions were common requiring constant
              vigilance.
 29 January 1945 "C" Company disposed its entire company sanding roads. A defined
              area of responsibility had been received from Group for Bn..
              Coverage. "B" Company also minus one squad which operated the Sand
              Pit worked its road assignment. "A" Company completed a 110' T/S
              Bailey Bridge in the vicinity of Schlindermanderscheid, with one
              platoon in reserve. A third platoon was on a working road patrol.
 30 January 1945 Two companies were given assignments of building a Bailey each.
              These bridges were of quite long length. "A" Company operated at
              Gilsdorf site clearing it of debris and mines preparatory to
              building their 240' D/S Bailey Bridge. "B" Company was preparing
              the second site at Bettendorf was a continuous Bailey and was to
              be 290' long and located at Bettendorf. "C" Company employed all
              platoons sanding roads and plowing. "A" and "B" Companies also had
              one platoon each on road hazard control. Experience in
              manipulation of the M-29 cargo carrier was being received by
              officers and men in headquarters. The vehicle is assigned to Gp.
              for appropriate uses. An accident investigation was in progress as
              to the disabling of a dozen or more men, one fatally, in a 6x6, 2
              Ton vehicle returning from an entertainment in Mersch. Battalion
              headquarters entertained Col. Keller accompanied by Capt. Martin
              both of the 1135 Engr. (C.) Gp.
 31 January 1945 The Bailey Bridge projects were continuing. "A" Company was at
              Giladorf with two platoons on the 240' D/S Bailey Bridge. The site
              posed some difficulties. One prior was not very satisfactory and a
              sudden thaw created a flood stage with a swift current hampered
              efforts to reinforce it. This in addition to lack of a readily
              available supply of lumber for cribbing. "B" Company's 290' D/S
              Bailey Bridge was progressing a bit more rapidly and was 25%
              complete at 1800 hours. The bridge at Gilsdorf was expected to be
              completed Feb. 4 and "B" Company's at Bettendorf 3 Feb. Operation
              of Sand Pit was taken over by one squad from "C" Company. The
              balance of the company was disposed on a road control. One platoon
              each from "A" Company and "B" Company also worked in there
              respective areas.
 |