| 1 December 1944 "B" Company placed a 70' D/S Bailey at Sarrewerden and during the
            process of putting tread on were ordered off the bridge due to
            proximity of small arms fire. "C" Company maintained a good share of
            responsibility for MSR. Due to distance involved radio
            communications were maintained with "B" and "C" Companies on both
            284 and 300 nets instead of phone. Reception was good.
 2 December 1944 A platoon of "A" Company moved to new quarters at Pisdorf. "A"
              Company also worked in road craters South of Riesdorf. At HQ plans
              to move more afoot. It is noteworthy that the personnel section
              usually termed the "Rear Echelon" preceded all of H/S Co. It
              spearheading a move to Sarrewerden along with a part of message
              center. "B" Company removed Treadway Bridge and built a fixed
              bridge East of Burbach. Over this bridge passed both Gen. Deger
              and Maj. Gen. Wood. The first with a direction to close off no
              traffic and the second proffered a compliment to engineer troops
              in general. "C" Company maintained the main supply routes in
              section leading into and North from Fenstrange.
 3 December 1944 Today was a bit irregular. "A" Company maintained its road
              assignment and moved to billets and a new CP at Zollingon. The
              command echelon invested new quarters at Sarrewereden at 1445
              hours. Upon setting up operations a quick dismantling and return
              to Fenstrange was ordered. The forward tactical situation suddenly
              altered making new station a bit untenable for maintaining
              Headquarters although S-1 Fwd and S-1 Rear remained at same
              location holding buildings for remainder of HQ for the next day.
              "B" and "C" Company in addition to road maintenance tasks each had
              a crater and culvert to pass traffic over. "B" Company in addition
              to road maintenance tasks also had a crater and culvert to pass
              traffic over. "B" Company had crater South of Rexingen and "C"
              Company had culvert near Burbach.
 4 December 1944 Congratulations were in order for Lt. Col. Reagan and Capt.
              McGlinchey. Plans were in a state of flux regarding future
              responsibilities and operations. However our engineer operations
              with 4th Armored were closing. All companies were in continuous
              work of road & bridge maintenance with "C" Company clearing
              debris from under Baileys at Fenstrange, Didendorf and
              Sarrewerden. The latter also constructed culvert NE of
              Sarrewerden. The personnel section continued in its quarters at
              Sarrewerden along with some elements of message center. A
              half-track mounted with 506 radio was attached to Bn. for ease of
              communications with Group.
 5 December 1944 "A" Company worked full tilt on road & bridge maintenance with
              one platoon dispatched to Norhange to check and clear new Corps HQ
              area of possible mine time bombs and booby traps. "B" Company
              maintained road from Sarrewerden to Sarre Union. "C" Company
              filled road craters in the vicinity of Rimsdorf-Domfessel and
              built a fixed bridge replacing Treadway SE of Sarre Union. Lt.
              Kuosynski was introduced to fellow officers at HQ.
 6 December 1944 Radio and operational procedures were being used at S-5. On many
              occasions it was the sole means of communications between HQ. and
              the companies. The 300 sets were especially useful. Bridges and
              the MSR's were with their maintenance a part of "A" Company's
              functions. One platoon was at work as yet with Corps preparing and
              making safe new quarters in Sarralbe. "B" Company moved its CP and
              elements from Niederstinzel to Sarre-Union. During the day it
              completed a culvert in place of 24' Tdwy in the vicinity of Sarre
              Union. "C" Company moved from Diedendorf to Diemeringen and also
              H&S from Fenstrange to Buscherhoff farm just South of Sarre
              Union. The former company was doing its share of MSR maintenance
              as well as sweeping for mines & posting roads so required.
              Their duties were enlivened by the capture of two of the enemy
              Farms and their usually numerous buildings seemed favored places
              for quartering operations section as well as H&S Co.
 7 December 1944 "B" Company was working a full schedule. Being in general support
              of divisional troops as a Bn. the goodly part of the missions
              entailed construction of culverts and fixed bridges replacing
              Tdwys. This company completed two. First was a 56' at Rahling and
              second 48' at Lorentzen. In addition to these "C" Company also
              placed two culverts 36' & 24' in length at Domfessel and just
              North of Lorentzen. "A" Company worked roads & bridges within
              the Bn. area for maintenance. Plans were to start for new
              locations at dawn. Our work in support of Fourth Armored Div. was
              terminated.
 8 December 1944 "B" Company moved into Willerwald in early morning hours and sent
              reconnaissance to bridge site in the vicinity of Sareinsming. 160
              ft. of Bailey Bridging with an intermediate bent was the solution
              decided on. 24 ft of Tdwy was laid out just prior to dark.
              Sporadic and uncontrolled F.A. fire was laid in the general
              vicinity until about 2100 hours when the FA fire, apparently
              controlled by some individual in the immediate area, began falling
              directly on the work site. 90' of the bridge was launched before
              the fire became so accurate and every effort at working on the
              bridge was met by a hail of fire. Col Reagan and Capt Monsione
              were sprayed with shrapnel at 2230 hours while at the site
              determining the advisability of continuing work. "C" Company was
              alerted to relieve the 60th Engineers on construction of 300 ft.
              of m-2 Steel Treadway Bridge and took over at dark. Sporadic
              uncontrolled F.A. fire was encountered throughout the site but
              fluctuation of the river stage and a restricting working area were
              the principle handicaps.
 9 December 1944 During the early morning hours every effort at completion of the
              Bailey was met with a hail of fire from F.A. After dawn the
              efforts of 3 or 4 men on the bridge were allowed to continue
              undisturbed but as soon as a platoon was put on the site a
              terrific barrage was laid down. The mornings casualties for "B"
              Company were 22 men and one officer injured. Occasional sniper
              fire was encountered so the efforts were abandoned until the town
              could be cleared. After civilians were rounded up and placed under
              guard work was resumed by a platoon of "A" Company. "B" Company
              being completely fatigued from 48 hours without sleep and the
              preceding 24 hours under fire. Sporatic fire ranged the river
              until completion of the bridge at 2245 hours. The uncompleted
              bridge had been damaged by the F.A. fire an extra hour was
              required to reinforce the damaged members. During the early
              morning hours "C" Company accomplished little of thier Treadways
              because of the fluctuating water stage hindering the approach, the
              restricted working space, the darkness, and harassing enemy fire.
              It was decided that ferries were the only crossing means. Just
              prior to noon the enemy discovered the operation and was laying
              heaving fire on the site.
 10 December 1944 "A" Company completed treading the 160 ft D/S Bailey at
              Sarreinsming and also constructed with Tread a 30 ft, S/S Bailey
              there. "B" Company rested while it cleaned up its well- used
              equipment as did "C" Company also. Bn. work was now completely in
              support of the 35th Inf. Did. for required engineer missions.
 11 December 1944 H&S Company in two echelons relocated its quarters. The
              forward echelon including the command established themselves 2
              miles South of Saarguemines in Town of Neufgrange. The rear
              echelon consisting of the motor and personnel sections planned
              move in the morning. The Battalion was on the alert being used as
              possible task force with Inf. Regiments. One platoon from "A"
              Company place an anti-mine boom in river to protect bridge at
              Sarreinsming.
 12 December 1944 In order to continue our operations the tactical situation needed
              clarification in the vicinity of Franenberg. The companies other
              than "C" Company made good use of the lull by taking on much
              needed rest and maintenance of equipment. "C" Company was working
              in direct support of the 60th Engrs. The pending task was the
              crossing of the Infantry over the Blies River in the vicinity of
              Frauenberg. Capt. Makholm took up new duties as S-5 as Capt.
              McCann was installed as the Executive Officer to fill Major
              Knight's position caused by his decease.
 13 December 1944 The Battalion was relieved of the contemplated bridge task at
              Saarguemines. The job had been delayed by intense mortar fire at
              the site. Our responsibilities and duties were ordered to maintain
              and furnish all necessary road & bridge efforts in rear of
              60th Engrs. "B" Company improved road North from Sarreinsming
              toward road Neunkirch filling in crater as well as on this road.
 14 December 1944 It was noteworthy that having built three bridges of prime
              importance the Battalion had put separate Divisions across the
              Saar River also. The first Bailey Bridge across the Saar River put
              4th Armored Division over at Fenstrange. The Battalion constructed
              Bailey at Diedendorf which placed the 26th Infantry Division on
              the opposite shore. The 3rd Division, the 35th Infantry, was
              crossed on Bailey at Sarrewereden. All companies were maintaining
              roads and bridges disposing a couple of platoons each in this
              work. The area involved was roughly North and East of canal
              bounded by Saarguemines, Neunkirch and Frauenberg road on North to
              tactical situation. On the South from Zetting, Wiesweiler, and
              Woelfling, Bliebruck road North.
 15 December 1944 Our usual routine efforts of road & bridge maintenance
              continued on in area North by East of Sarreinsming. "B" Company
              swept and posted road clear of mines from Woustviller Northeast to
              Welferding. Two Baileys were in our program. "C" Company completed
              D/D 100' Bailey Bridge with Tread at 0815 hours and improved the
              approaches. This bridge was built close to a draw with town of
              Habkirchen on far side held by the enemy except for three houses
              in close proximity to the bridge. These were held by our Infantry.
              This bridge was not discovered by enemy until it was completed
              just after light of day. Upon discovery the enemy let mortar in as
              well as F.A. shells which dropped in Frauenberg during the
              operation. The mortar fire was short. "A" Company put in a Class
              70 T/D Bailey Bridge 110' in Saarguemines unmolested in any great
              degree by enemy fire. It was only 60% complete at 1800 hours. Work
              continued during the night though delayed by the bogging down of
              vehicles bearing panels to bridge site.
 16 December 1944 The 110 ft T/D Bailey was entirely complete by the two platoons of
              "A" Company at 1000 hours. The remaining platoon placed ?? this
              class of bridge. While one platoon of "B" Company looked after the
              equipment two platoons were continuing road and bridge maintenance
              in the vicinity of canal and river in Saarguemines. "C" Company
              recieved 100' D/S with one platoon at Frauenberg with one squad
              remaining for maintenance. Two platoons maintained road out of
              Sarreinsming Northeast to Ft. Tiesing Farm. This route required
              much repair and was of high priority.
 17 December 1944 Despite possible enemy discovery and resultant shell fire a 132
              ft. Floating Treadway was placed at Reinheim. It required work
              throughout the night and was finished at 0815 hours. This was
              accomplished by "B" Company. Tread was placed on D/D 100' Bailey
              at Frauenberg by "C" Company. The approach was extended on the
              near shore from 10' to 20'. "A" Company maintained and improved
              road from Wiesweiler to Bliebruck on to Folpersweiler. Work was
              commenced at Gersheim at 1930 hours on a 70' D/S Bailey. One
              platoon put in a 22 ft fixed bridge replacing 24' Tdwy. During
              this construction a 24' Treadway was placed to by-pass this
              operation. "I" beams long transported were finally used up by "A"
              Company at this Bliesbruck bridge.
 18 December 1944 "A" Company completed the 80' D/S Bailey at Gersheim at 0200
              hours. Also a minefield was marked and taped off at road
              intersection of Hermekappel. An anti-mine boom was placed in the
              Blies River at Reinheim by "B" Company. This boom 110 feet long,
              was the second one built in an effort to eliminate any floating
              mines destroying bridges. The initial one was at Sarreinsming 250
              feet long. "B" Company in addition put a culvert in at Ebersing
              and maintained road from Wiesviller to Bliesbruck and Hermeskappel
              to Neunkirch. "C" Company marked and taped off a suspected
              minefield in Le Grand Bois and improved and maintained road from
              Sarreinsming North-East through previously mentioned forest. An
              S-mine in the aforementioned field caused fatality to Sgt. Cassidy
              and the severe wounding of Lt. King.
 19 December 1944 The 50' D/S Bailey was in major portion completed with a culvert
              replacing it. This located just East of Folpersviller. While two
              platoons were occupied in this task two squads were posting and
              clearing minefield in the vicinity of Hereskappel. The remaining
              squad repaired approaches to Infantry support bridge West of
              Bliesbruck. It had been made difficult to use by the change in
              river's stage. "B" Company maintained its area roads &
              bridges. Two platoons were disposed in this mission North and East
              of Wiesviller. Also the anti-mine boom was moved 200 yds. upstream
              from Reinheim. The task of fencing minefield with barbed wire in
              Le Grand Bois was completed by "C" Company.
 20 December 1944 One platoon of "A" Company was alerted for a combat mission. A
              second platoon was assigned to the maintenance and repair of roads
              and the clearing plus posting of minefield in the vicinity of
              Hermeskappel. "B" Company continued its efforts improving the
              roads assigned from Neunkirch South and East. One platoon remained
              in reserve. A party consisting of squad were maintaining 160'
              Bailey at Sarreinsming. The main portion of "C" Company was in
              continuous maintenance of roads and bridges. The road from
              Sarreinsming Northeast through Le Grand Bois proved very
              troublesome. Conditions and drainage of road plus being only one
              way made it a struggle to keep passable.
 21 December 1944 The 50 ft. Bailey was finally removed just East of Folpersviller
              upon completion of culvert. In addition to their road maintenance
              50% of minefield in the vicinity of Q588558 was cleared and
              posted. One platoon of "B" Company was alerted and sent on mission
              of patrolling hill 280, West of Hambach. The remainder of the
              Company worked roads South and East of Neunkirch. "C" Company was
              completely absorbed in bridge and road maintenance. A half squad
              worked on 160' Bailey at Sarreinsming.
 22 December 1944 A complete change of area was made in conjunction with Corps
              movement. The operation started at 0600 hours with final
              destination reached 1500 hours. This was at Bertrange in
              Luxembourg 2-1/2 miles west of the city. Eight additional 2 -1/2
              ton cargo trucks were dispersed among the companies. These were
              loaded with approximately 130 PCS of flouring each for transport
              for Group.
 23 December 1944 No vital operations were in action. The Bn remained on the alert
              for contemplated move. Arrangements to relocate in the vicinity of
              Mersch were held in abeyance until tomorrow morning. Col. Reagan
              reported Bn would have duties now as support of the 10th Armored
              Division.
 24 December 1944 All companies moved. H&S and "A" Company found CP quarters in
              Rollingen. "B" Company set up in Beringen and "C" Company in
              Udingen. These localities were adjacent to Mersch. Overlays
              showing areas for reconnoitering were handed to "A" and "B"
              Companies. Demolitions were to be prepared for all bridges and
              culverts in this prescribed area. "C" Company was placed on the
              alert to build an 80' D/S Bailey South of Ettelbruck.
              Reconnaissance of this bridge site was being made until
              construction was tactically allowable.
 25 December 1944 "A" and "B" Company were active preparing barriers for placement,
              hasty minefields and prepared bridge demolition charges. "A"
              Company prepared five bridges for demolition in area Northeast of
              Mersch. Four hasty minefields were also prepared for placing into
              position in same general vicinity. North of Wedernach an abatis
              was prepared with trees notched and explosives in place. "B"
              Company also placed charges preparatory to demolishing some
              bridges and culverts amounting to nine in an area East and North
              of "A" Company. "C" Company was on the alert maintaining and
              cleaning while awaiting order to erect Ettelbruck Bailey.
 26 December 1944 The tactical situation remained unaltered. The Bn. continued its
              labors preparing and stationing guards on demolition charges and
              mines. Minefields and abatis were also completely prepared for
              future effective placing in this area. "C" Company was in reserve
              maintaining its equipment. The Bailey Bridge at Ettelbruck awaited
              construction orders from Division Engineer.
 27 December 1944 "A" and "B" Company continued preparing demolition placements. In
              order to effectively blow bridges "A" Company dug in back of the
              abutments on the bridge south of Chateau de Bertrange. "A" Company
              worked a total of 16 locations in the barrier plan. "B" Company
              employed its compressor in preparing abutments on the river bridge
              South of Fels. Both Companies put guards on the charges. "B"
              Company prepared 18 different sites in planned barrier zone. In a
              switch of division positions 6th Armored replaced the 10th and Bn.
              was therefore now in support of last named for any engineer tasks.
 28 December 1944 No additional assignments were given to the Bn. Alerts continued
              on bridge demolitions and hasty minefields and maintaining
              security on explosives. All three platoons of "A" and "B" Company
              were thus employed. "C" Company reverted to normal status after
              having been alerted for some days awaiting mission of Bailey
              Bridge construction at Ettelbruck. This task did not become
              pressing and was canceled.
 29 December 1944 The Bn. was partially relieved by the 133rd in support of the 6th
              Armored. The Bn. thus reverted to a status of general support. "A"
              Company was relieved of their duties guarding explosives and five
              points for demolition on left flank in area of Easingen and
              Udingen. "B" Company was relieved 100% of its responsibilities on
              the Northern flank. "C" Company started hauling sand, supplies to
              the south-west of Finsterthal. A shovel was placed here and the
              sand was stockpiled along roads for ice control at perilous
              points.
 30 December 1944 "C" Company continued its assignments of hauling sand and
              arranging stockpiles along MSR's and secondary roads at strategy
              points. These to be used for ice control. "B" Company effected a
              clean-up of its equipment upon being relieved of its previous
              duties in conjunction with preparing and guarding points for
              demolition and explosive charges. "A" Company relinquished its
              task at 1630 hours to the 133rd Engrs. With this done the Bn. was
              100% in general support of 6th Armored Division. No further
              responsibility was therefore expected for the prepared positions
              placed with accompanying adjacently located explosives serving as
              a defensive barrier.
 31 December 1944 Being general support for III Corps the Bn's main effort at this
              point was to keep supply routes open to traffic. Some snow had
              fallen coating the roads and making them hazardous. "A" and "B"
              Companies together employed ten trucks hauling sand from pit in
              the vicinity of Finsterthal to control the icy conditions. The
              major portion of "A" Company being in reserve tended to its
              equipment. "B" Company used one platoon and two trucks and
              completed task of hauling wire for Drawbridge at Angelsberg. "C"
              Company hauled approximately 250 yrs.- 100 loads of sand for MSR's
              and second routes.
 |