| 1 February 1945 "B" Company's two platoons were progressing on the 290' D/S Bailey
            Bridge at Bettendorf. 40% of the task was done with 3 Feb the
            estimated completion date. The 240' D/S Bailey Bridge at Gilsdorf
            still posed its difficulties with a continuing flood stage and
            accompanying ice flows and a rapid current. The required welding of
            cap stills and transoms was being performed by the motor section. A
            second arc welder was procured for the job. "A" Company resorted to
            a high line at Gilsdorf to transport materials too intermediate
            piers when boats became a liability. Roads were being watched by all
            platoons from "C" Company minus one squad employed at Sand Pit. A
            good part of their effort was the stock piling of sand along
            potential hazardous sections.
 2 February 1945 Flood conditions in the river contained fixed bridge destruction
              potentialities. Reconnaissance of needed requirements against any
              eventualities was made. "C" Company placed guards on fixed bridge
              at Colmar. 85% of Bettendorf 290' Bailey Bridge of "B" Company was
              done. Work was still going on at Gilsdorf on the piers and
              cribbing. Drainage and minor road repairs apparent after the thaw
              was being done in Bn. Assigned area of responsibility by platoons
              from "B" and "C" Company's.
 3 February 1945 Steady progress on "A" Companies continuous Bailey Bridge of 240'
              at Gilsdorf was made. The Launching was expected to start at noon
              tomorrow. Bettendorf Bailey Bridge of 300' which is to be 130' D/D
              and 170' D/S was opened to class 40 traffic at 1800 hours.
              Approximately 80' of approach ramps were used on the bridge. Some
              welding was still required and being done. "C" Company maintained
              patrols along roads of the Bn. assigned areas & guarded bridge
              located at Colmar. Having no vital need of sand the squad
              operating Sand Pit west of Mersch was relieved. Equipment was
              permitted to remain with on non-com in charge in order to hold it
              for use whenever necessary.
 4 February 1945 "A" Company commenced construction work on Bailey itself with the
              starting of the launching move. With this 80% of bridge complete
              traffic was expected to move over it by 1800 hours tomorrow. At
              Bettendorf "B" Company put the final weld on their bridge. A 80'
              D/S Bailey was specially built at Reisdorf by "C" Company. It was
              started at 1730 hours and done at 2300 hours. This was over the
              Sauer River. Reconnaissance was made of bridge and area for an
              assault crossing at Wostroff. The information was procured
              although Lt. Swenholt, our recently assigned Recon. Officer, was
              injured by enemy action. drainage and minor repairs on roads in Bn
              assigned area was furthered by one platoon from "B" and "C"
              Company.
 5 February 1945 Due to preparations and preliminary work required for impending
              operations "A" Company was relieved of it's assignment of
              Bettendorf Bailey Bridge. The 1303 Engr. took over the remaining
              fractional section to bring it to completion. Demonstrations to
              the 319th Inf. Of the use of Inf. Footbridge and assault boats for
              river crossings was made by a platoon from "A" and "C" Company.
              "B" Company was alerted for an assault boat river crossing as well
              as "C" Company. "A" Company was assigned task of constructing
              reinforced Footbridge. The river to be crossed was the Our. A
              forward CP to facilitate command and operations was set up at
              Bettendorf for above named missions.
 6 February 1945 With the forward CP of the Bn. set up in Bettendorf operations
              functioned through it. All companies were occupied hauling
              equipment into position for river crossing. Two platoons of "A"
              company hauled Infantry footbridge into Hosdorf. "B" Company
              hauled boats to a point southeast of the same town along the Our
              River. The assault mission was to commence in the darkness of
              early morning at 0200 hours.
 7 February 1945 The battalion was engaged in the assault crossing of the Our
              river. One platoon from "C" Company of the 179th Engrs assisted
              with two platoons held in tactical reserve. The assault was made
              on a somewhat broad front stretching from Hosdorf to a point 1 1/4
              miles South and East on the river. A measured success was achieved
              in getting some elements across. Plans were to put in a reinforced
              Foot Bridge as soon as initial elements had landed. However this
              was not brought to a realization due to a current of about 12
              miles per hour. Strong persistent as well as accurate enemy small
              arms and shell fire was also a decisive reason as it was directed
              from interlocking trenches on opposite shores. These circumstances
              made continued use of boats necessary. Exhaustion and loss of
              equipment combined with the fact swollen stream made this
              operation a most difficult one.
 8 February 1945 With the Bn. Assault operations in any scale only possible during
              the dark of night more elements were scheduled to make the
              crossing. No foot Bridge was yet built. A number of light
              casualties from flying fragments were reported. Supplies were sent
              over in boats including food and ammunition.
 9 February 1945 Operations continued at Hosdorf crossing. "B" Company took up the
              task of evacuating wounded and sending over supplies for the
              infantry. Plan adopted was to use but four assault boats in this
              process. A section of rope was tied to each end of the boat with
              working parties hauling boats in the desired direction from each
              shore. This was found to be a workable solution to the problem of
              overcoming swift stream. Much effort was going into this assault
              mission and many handicaps prevented a foot bridge from being
              placed to further support the operation. "C" Company moved out to
              Dillingen preparing to put in a floating Treadway. This to be
              started in the night.
 10 February 1945 "F" Company 317th Inf. Conducted fire fight 200 yards from bridge
              supported by Tank 75's and 50 calibers. Resistance cleared before
              dark and bridge started at 1800 hours. Guy cables were strung but
              work was held up by F.A. fire which knocked out power boat at 2200
              hours. Five floats with cables were in water by dawn.
 11 February 1945 Work continued but slowly. More cables were strung. Breakdown of
              crane and power boat failure served to further slow operations.
              Estimated 8 to 10 ft. /sec. current made it inadvisable to launch
              bridge without adequate guys to hold in place. Work suspended
              during night because of hazard of losing bridge already
              constructed. "A" Company replaced "C" Company 1600 hours.
 12 February 1945 Work continued and by dark all floats were in place. Rise of water
              surface extended bridge approximately 75 ft. Approach ramps put in
              place overnight proved to work extremely well.
 13 February 1945 River at flood stage caused complications on approaches. Some
              Treadway Bridge trucks and Bailey bridging was passed to repair
              road on far side. Medical traffic was allowed while approaches
              were being completed. All traffic was allowed to travel on bridge
              at 1600 hours while work continued on approach and placing
              trestles under floats. "B" Company replaced "A" Company 1500
              hours.
 14 February 1945 Trestles placed under floats continued. Completed 1800 hours by
              "B" Company. Approaches still being worked on, water receding.
              After reconnaissance proved site clear "A" Company prepared site
              for 110 ft. T/S Bailey Bridge in the vicinity of Wallendorf of two
              craters along same road. "C" Company went to work on construction
              of 290' D/S Continuous Bailey Bridge at Wallendorf at confluence
              of Our and Sauer Rivers.
 15 February 1945 The 110' T/S Bailey Bridge was completed North of Wallendorf on
              Gaybach R. at 1945 hours. Some shell fire was encountered but not
              sufficient to hamper the task in any major degree. "C" Companies
              240' D/S Continuous Bailey Bridge at the confluence of Sauer and
              Our Rivers in Wallendorf was progressing with 20% for its
              construction done. "B" Company worked on the roads starting at
              Fels to Christnach thru Waldbillig to Haller. One squad was
              employed also on approaches to Treadway at Dillingon for
              maintenance.
 16 February 1945 "C" Company resumed work on the 240' Continuous Bailey Bridge at
              Wallendorf. Bent construction was similar to Bettendorf bridge.
              Welding was again done by the motor section of all the crib
              stills. Completion was estimated at 1800 hours on the 17th One
              squad from "B" Company swept road from mines along river North of
              Wallendorf. Roads from Fels to Dillingen in Bn sector were worked
              over by "A" Company.
 17 February 1945 "A" and "B" Companies were engaged in road maintenance with
              Company "A" working from Wallendorf to Reisdorf to Frusdorf. "B"
              Company employed men on Fels road to Mendernach and Ermsdorf. All
              companies received minefield clearing assignments which were
              partially completed. Work continued on those fields which were
              both friendly and enemy. Two platoons brought the Wallendorf 250'
              Continuous Bailey Bridge to completion at the 1630 hours. Major
              Mersweiler was presented to the headquarters as Bn. Ex. Officer.
              Lt. Kuczynski was reassigned as the Rcn. Officer.
 18 February 1945 The Rock Crusher and quarry started production at Bettendorf. "C"
              Company furnished one squad for its operation. One platoon worked
              roads from Fels to Ermsdorf. The company was placed on alert to
              put Bailey of 80' D/S on Gaybach River road. "B" Company completed
              its 110' T/S Southwest of Wallendorf at 2015 hours. The assignment
              of clearing a friendly mine field was completed by "A" Company at
              1730 hour.
 19 February 1945 "B" Company went to work on 140' Bailey Bridge at Mostroff and its
              dismantling. 100' was T/S and 40' D/S. Treading was placed on 110'
              T/S Bailey on road to Mostroff. A squad from "C" Company operated
              Rock Crusher in Bettendorf quarry. "A" Company maintained all
              Battalion roads assigned. Both "A" and "B" Company had one platoon
              each clearing mines. Capt. McCann left Bn as S-3 to report to
              Group as Asst. S-4.
 20 February 1945 The Diekirch, Medernach, Fels road and route just North of Sauer
              River from Diekirch through Bettendorf to Wallendorf was being
              maintained by "A" Company. "C" Company had major part of company
              clearing mines. One squad finished Tread on 110' T/S Bailey Bridge
              at 1600 hours.
 21 February 1945 "B" Company maintained the roads of Bn. area using all its
              platoons. Emphasis was placed on shoulder conditions using rock
              from Bettendorf quarry. Minefield clearing, both friendly and
              enemy, occupied all of "C" Company. One squad from the company was
              employed in operation of rock crusher in Bettendorf.
 22 February 1945 Routine operations continued with road repair and demolitions our
              main tasks. One squad from "A" Company worked the rock crusher at
              Bettendorf quarry. One platoon of the company repaired and
              maintained the road section from Diekirch to Medernach and Fels in
              additions to two squads. A third platoon cleared friendly mines
              and demolitions. "B" Company maintained a second stretch of road
              from Diekirch East to Bettendorf, Mostroff to Wallendorf. Also
              from Reisdorf Southwest to Ermsdorf and Wedernach. "C" Company was
              in reserve cleaning and maintaining their equipment.
 23 February 1945 Interesting demolitions in blowing pillboxes were going on. "C"
              Company destroyed four using 3000 lbs of explosives in the
              process. These pillboxes were located just north and west of
              Wallendorf. The purpose was to make them uninhabitable and
              unprofitable to reconstruct. "B" Company dispatched six men
              equipped to clean and repair Corps HQ at Fels. The routine but
              important road repair included filling a good sized crater near
              Roth continued.
 24 February 1945 "A" Company completed their D/D 180' Bailey Bridge south of Roth
              at 1630 hours. Work of treading bridge was finished during the
              night. A squad was on the posted road landing South of Bettal to
              Roth. "B" and "C" Company maintained roads in area of
              responsibility. "B" Company kept one squad at Rock Quarry and used
              another to construct culvert as grater on road between Bettal and
              Roth. "C" Company continued blowing enemy pillboxes.
 25 February 1945 The prosaic but vital duties and missions continued. Main efforts
              were the maintenance of roads and this required a good bit of
              effort. All platoons of "B" Company and one platoon and one squad
              from "C" Company were employed in this task. Demolition of
              pillboxes and mine sweeping along road and shoulders as well as
              clearing both enemy and friendly minefields were the task which
              "A" company and the balance of "C" Company were doing. Plans were
              made to move forward in support of 4th Armored division.
 26 February 1945 The battalion with all its companies moved to forward positions to
              effectively operate in support of the 4th Armored Division. "A"
              Company constructed 100' Bailey (T/S) at Oberweis. Completion was
              reached at 1315 hours and Tread was on at 1430 hours. A Third
              platoon filled crater and collected materials for a fixed bridge.
              "C" Company maintained the regular assigned road area. "B" Company
              cleared and maintained MSR.
 27 February 1945 "A" Company filled crater installing culvert at Oberweis. A second
              platoon widened and floored a 36' Treadway at same town. The first
              platoon repaired and maintained road from Niedergeckler to
              Outscheid. "B" Company maintained roads from Roth to
              Niedergeckler. One platoon of "C" Company repaired roads from
              Neuhaus to Oberweis. A second platoon repaired existing bridge at
              Rittersdorf.
 28 February 1945 Road repair and its continued maintenance was a big factor in the
              battalion tasks. Many craters were prevalent blocking or making
              roads passable only one-way. Two platoons from each of the
              companies were therefore assigned road areas for repair. One large
              repair was being made by a platoon from "A" Company on crater at
              Oberweis. A culvert pipe was emplaced and fill was expected to be
              complete at 2100. "C" Company reinforced bridge at Rittersdorf
              with one squad. "B" Company was assigned the construction of an
              80' D/S Bailey at Stahl.
 |