| 1 November 1944 The battalion D-7 Dozer now has armor plating on operator's cab,
            also required a change to a 20-ton trailer for transporting same.
            Cold was sufficient to make a probable freeze come about. The
            drivers therefore emptied water from their radiators. The road net's
            major difficulties liquidated, efforts were now placed on widening
            certain sections. ASP areas were being stocked between Champenoux
            and Erbeviller.
 2 November 1944 The rotation of companies at rock crusher was discontinued. Each
              company having had a day for care and cleaning of equipment, now
              reverted to placing two platoons on duty, having one as reserve. A
              wood-burning stove was installed in the operations tent. Tire
              patches being scarce there is a possibility of deadlined equipment
              due to tire failures.
 3 November 1944 A 2 ton dump truck of Company "C" was made unserviceable due to a
              tank hitting it. Headquarters continued placing steel netting in
              the muddy areas of bivouac to make walking more convenient to
              frequented points. The maintenance of main supply routes and
              secondary roads of the Bn. area remained our prime duty.
 4 November 1944 Lt. Edmonston was directed to serve as Liaison Officer with 4th
              Armored Division Headquarters. An officers call was held at which
              time impending new operations were discussed and newly assigned
              officers to the Bn. were introduced. Among the latter was Lt.
              Oldre, the first battlefield commission made within our Bn. The
              Red Cross Clubmobile again was welcomed to the Bn. with its coffee
              and doughnuts.
 5 November 1944 Evidences in the battalion showed new impending operations were
              due. Preparations were on to put all things in a very mobile
              condition. Map segregation and proper distribution kept S-2 well
              occupied. A report came that Lt. Edmonston was a victim of an
              accident and Lt. Villadsen was sent to replace him.
 6 November 1944 The battalion was relieved of its current areas of road
              responsibilities with Engineers of 1157th Group assuming the task.
              The new priority roads for maintenance included main routes
              bounded roughly West by Sorneville - Pettoncourt road, East by
              line drawn according to tactical situation, North by Pettoncourt -
              Chambrey road and South by Sorneville-Bezange road. Group moved to
              Moncel today with Lt. Grey maintaining Liaison.
 7 November 1944 Priority on production at "B" Company's quarry at Remereville was
              given solely to 24th Armored Engrs. All flame-throwers were
              ordered returned to Third Army. The operations dug-out finally
              required evacuation. Weather deteriorated so that drainage was
              overtaxed by day and night rains despite use of a booster pump.
 8 November 1944 Activities increased with "A" Company preparing approaches and
              commencing Bailey bridge construction at Chambrey. Flood control
              along dikes from Bioncourt to Brin was "C" companies main effort
              plus road maintenance and operation of Remereville rock quarry.
              "B" company remained on the alert to move.
 9 November 1944 The 110' Bailey bridge was completed at Chambrey. A change of area
              and quarters proved an advantage. The Burthelcourt Chateau also
              billeted Headquarters Operations. "B" Company was ready to move to
              24th Engrs. area. "C" Company continued its prior assignment. The
              reconnaissance section was of paramount importance and ably
              constructed during these particular days.
 10 November 1944 A full schedule found "C" Company completing its 50' Bailey at
              Sallonnes. Bridge was started at 1400 hours, material arrived at
              1600 hours. The bridge erection was complete at 2000 hours. It was
              a very good and rapid piece of work. "C" Company besides mine
              sweeping and road repair also erected a Treadway bridge in
              Sallonnes. "A" Company removed a 1500' abatis and farm machinery
              road block in Chateau-Salins. Also putting tread on Chambrey
              Bailey. "B" company is as yet detached to work and travel with
              CCB.
 11 November 1944 No moment lacked activity. Numerous reports of enemy minefields on
              through Chateau-Salins North to Lubecourt kept "A" & "C"
              Companies well occupied clearing roads of mines and posting signs.
              "B" Company was on the march with CCB. Chateau-Salins in a second
              visit by the battalion was overhauled for enemy obstacles while
              plans were afoot to move further East. The Recon section bolstered
              the whole units morale when Lt. Christiansen with T/S Szychulski,
              T/4 Castle, T/5 Pitts, and Benoit found themselves in a bee-hive
              of sudden retreat as a part of enemy troops in Vaxy. Finding cover
              in a corner building they eliminated the enemy troops in Vaxy.
              Finding cover in a corner building they eliminated the enemy
              troops plus destroying a staff car and a halftrack. A complete and
              calmly executed ambush.
 12 November 1944 No longer was it a muddy area but proper housing which interested
              us in claiming quarters for billet and operations. Even the dead
              had to be removed to furnish proper areas to function. "B" Company
              reported their 4 ton prime mover damaged with trailer and the 1st
              platoon had received eleven casualties, one fatal due to harassing
              artillery fire. Mines, road and bridge maintenance in area from
              Sallonnes North and West to Fresnes and Northeast to Morhange and
              Conthil. New quarters were established at Gerbecourt 2 miles North
              of Chateau-Salins at 1000 hours.
 13 November 1944 "A" Company was now located in new quarters in Lupecourt. "C"
              Company was well occupied sweeping for mines North of
              Chateau-Salins and building a Treadway bridge in the vicinity of
              Brehain. Also repaired tank trap near Vaxy. All roads were being
              thoroughly traveled by much and heavy traffic. First snow fall
              scarcely covering tilled fields. Homes now being reached were
              completely abandoned. Enemy it seemed were crowding all civilians
              ahead of them as they withdrew.
 14 November 1944 Two of the more noteworthy happenings were the surrender to the
              reconnaissance, several of the enemy troops, one a casualty and
              the explosion of a mine by an R-4 dozer on job with Lt. Sultrom in
              the vicinity of Brehain. Operator though blasted clear, was
              unhurt. A third incident would be the bogging down of D-7
              requiring a ten ton wrecker to free it. Besides filling a
              good-sized crater "C" Company constructed two bridges, 48' &
              56' long, North and South of Brehain. A 50 ft. D/S Bailey bridge
              completed "A" Company prepared approaches for a second Bailey
              bridge North of Hampont plus usual road maintenance and mine
              sweeping routing - an important detail though not unusual. 250 new
              sleeping bags were issued to the letter companies by S-4. Other
              men received one added blanket each.
 15 November 1944 A good portion of engineer effort on the battalion work sheet
              included Bailey and Treadway bridges, abatis, road blocks and
              several large craters. Major Knight visited "B" Company in the
              vicinity of Sotzeling. Capt. Monsione related how the Company had
              furnished security for artillery units, cleared mines and road
              blocks in support of CCA. Morale was high and company was happy to
              receive rations and new bed rolls. Battalion D-7 was again in
              operation. Corps received a squad with mine detectors from "A"
              Company to clear its headquarters area beyond doubt in
              Chateau-Salins.
 16 November 1944 Work was afoot all along the traveled routes. Minefields were
              everywhere being destroyed and all barriers and blocks leveled.
              Lt. King found some previously undiscovered S-mines in the
              vicinity of Aichen. Two fatalities were removed by Lt. King and
              remaining mines were marked and eliminated. Lt. Martin working
              with a squad in and about Corps HQ. discovered a formidable
              arsenal. It added up to over 500 mines, bazooka shells and varied
              firing devices. "B" Company was contacted regularly as it worked
              along with CCA. One day of sunshine was a most bracing element and
              every bit welcomed.
 17 November 1944 Operations continued with units practically exchanging quarters. A
              4th Armored Medical unit took up the battalion's quarters at
              Gerbecourt as Niverlach - two miles South of Morhange - was
              established as Battalion CP at 1600 hours. With "B" Company
              released from its assignment with CCA and located at Haboudang.
              "C" Company in turn was attached to the 2nd Cavalry. Its CP was
              located in Rechicourt. A new and quite extensive area for
              operations was given the battalion. It stretched West to Bausemont
              and Bathelemont, Chateau-Salins North and East as far as was
              tactically possible. Our southern boundary again paralleled the
              canal at Parroy.
 18 November 1944 Up until now the battalion had been at work straddled on the
              limits of the 35th and 26th Inf. Divisions. Now it is in general
              support of 26th Division along with "C" Company detached. "A"
              Company completed a single double 40' Bailey South of Puttigny as
              well as placing tread on ramps on Hampont Bailey and removing road
              block between Haraucourt and Mulcey. Efforts to find new locations
              were less difficult due to the enemy evacuating all civilians.
              However the numerous friendly troops in turn caused congestion.
 19 November 1944 Varied offensive operations were impending. Armor awaited dawn to
              thrust out which required construction of two Bailey Bridges S/S
              (20' and 30') along route from Haraucourt to Mulcey. "A" Company
              was called and had bridges ready at 0300 hours, "B" Company
              maintained roads in sector drawn from Chateau-Salins to
              Burlioncourt to Hampont and Norville. "C" Company operated with
              2nd Cavalry Group clearing mines and laying Treadway bridging.
              During the day Major Reagan relinquished his atipathy to hospital
              confinement and went for a rest to overcome persistent cough and
              feverishness.
 20 November 1944 Night operations were more prevalent. "C" Company still attached
              to the Cavalry place two Treadway bridges completing the dual
              operation by 0500. The first was over the Marne Canal and the
              second on the Mulcey - Dieuze road. They were 18 and 31 feet
              respectively. Mine sweeping and road maintenance was a cardinal
              point. "A" and "B" Company filled their day on this Bn. work.
              Preparatory investigations were on to find quarters to take up
              operations nearer responsibilities assigned Bn.
 21 November 1944 New quarters were now placed in Dieuze. Established at 1500 hours.
              Armor had found the enemy in speedy withdrawal. This caused a bit
              of a problem to furnish "C" Company, racing on with the calvary
              its proper rations. "B" Company maintained its road net with "A"
              Company placing a 48' Treadway and 80' Bailey in Dieuze. The
              bridges were commenced at 2100 hours Nov. 20 and completed 1115
              hours today. "C" Company with all platoons and squads partialed
              out to the various. 2nd Cavalry troops pulled mines both Riegel
              and S mines in the vicinity of Lagarde. Reconnaissance was in
              operation to maintain intelligent information regarding possible
              coming areas for work and its requirements. "B" Company
              constructed one 10' D/S and one 40' D/S vicinity of Dieuze.
 22 November 1944 "A" Company completed a 60' D/S Bailey between Lostroff and
              Guinzeling. In addition mines and road blocks and bridge
              maintenance kept the whole company busy. "B" Company was also
              maintaining its section of road area. "C" Company was traveling
              fast with the Cavalry tearing out abatis, placing Treadway Bridges
              and a timber bridge. The command echelon made plans to move on to
              Domnom.
 23 November 1944 The usual bridge and road efforts were conducted by "A" and "B"
              Companies. The command echelon moved on to Domnom and quartered
              itself and the CP there at 1500 hours. Communications were well
              exercised in stringing wire to properly receive information.
              Distances were sometimes quite lengthy to complicate matters.
 24 November 1944 Perhaps one of the more troublesome sites at which a Bailey was
              constructed was the 100 ft. T/S at Fenstrange. The job required 24
              hours constantly interspersed with mortar and artillery fire. "A"
              Company worked hard to complete the bridge. Many large and
              far-stretching defensive features were now being encountered with
              "B" Company at work filling in one of them - an anti-tank ditch.
              This was placed just West of Mittersheim. Also repaired ramps over
              canal just before entering the same city. "C" Company was taken up
              with activities in conjunction with 2nd Cavalry. "C" Company
              commander paid regular daily visits to HQ.
 25 November 1944 After blasting a house in part to get fill "A" Company continued
              improving the bridge approach which task required a 50' radius of
              roadway. In the process two men received shrapnel wounds and two
              became fatalities. The 4-Ton prime mover was also destroyed in
              Fenstrange by heavy artillery fire. "B" Company maintained
              Treadway bridge at Mittersheim and widened and completed filling
              in anti-tank ditch further West on same road.
 26 November 1944 "B" Company was placing a fixed Timber Bridge in Mittersheim and
              maintaining filled crossing of anti-tank ditch. A culvert was
              constructed in Fenstrange also. "C" Company was still detached.
              "A" Company put finishing touches on their Bailey Bridge approach
              and its maintenance. New sites for billeting the Bn. were in
              process of investigation near Fenstrange. Shells from artillery
              were yet too much in evidence.
 27 November 1944 Quarters for operations and all of H/S were set up at Pontency
              farm just East of Fenstrange. "A" Company arranged their place in
              Fenstrange proper. "C" Company was in a major portion being
              occupied by a minefield in area of defensive entrenchments and of
              Mittersheim which procedure was at the expense of platoon Sergeant
              Kazner's death. "C" Company stationed at Berthelming returned to
              Bn. duty from 2nd Cavalry Group. It was noticeable how territory
              with its elements were growing increasingly indifferent, even
              non-sympathetic.
 28 November 1944 Verbal commendations proffered by Gen. Patton at Fenstrange Bailey
              Bridge site was of a distinctive nature for the men on the job.
              This 100 ft. T/S Bailey was the first to span the Sarre River and
              was constructed by "A" Company covering a 24 hour period. A Stars
              and Stripes reporter paid a visit to the officers and EM of this
              Company also. "B" Company cleared over 270 Riegal mines today in a
              field of 1000 or more. "C" Company finished a 100' Bailey Bridge a
              bit further North on the Sarre at Diederdorf. Besides the vital
              Bailey construction all companies were employed sweeping road and
              shoulders on all MSR and alternate routes of our area.
 29 November 1944 Mines have been "B" Company's nemesis the last days. They
              continued work on the large field of Riegal mines near
              Mittersheim. "A" Company was at work sweeping, posting and
              draining roads North and East of Fenstrange. "C" Company
              maintained the MSR from Corps rear boundary to Fenstrange.
 30 November 1944 The care and cleaning of equipment was on the agenda during the
              lull prior to impending offensives. "B" Company completed its task
              of clearing the extensive field of Riegels in the vicinity of
              Mittersheim. "A" Company & "C" Company were engaged in road
              and bridge maintenance. Awards were being received within the Bn.
              in plentiful number. Quarters were becoming more scant as the
              actual German border was being neared. The many troops made
              constant and prompt moving essential. The maintenance section did
              good work in acquiring a 2 ton shop truck with appurtenances. Also
              they arranged so that each Company was now equipped with their 4
              ton prime movers again.
 |