Incidents, Messages, Orders, Etc. |
1 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C, Third platoon working on runway, leveling and drainage. H&S CO. A.D.E. and S-3 Sections working and surveying airport area. We had a nice clear day with even sunshine for a change. |
2 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C, H&S Co. A.D.E. & S-3 section surveying airport. Slightly cloudy yet warm today. |
3 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C, H&S Co., Today was cloudy and windy and somewhat cold. |
4 February 1944 |
Kingston, Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C, H&S Co., The mud is drying which will help construction. Aside from the wind it was a nice clear day. |
5 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
The disposition of the Platoons and the work is the same as Friday the 4th of Feb. 44, however it's a much pleasanter day. Sun is shining and getting warmer. The mud is drying considerable and makes working condition much better. There are going to be three blister hangers and two Butler hangers at the Airport. The 342nd Engr. Regt. is supposed to erect the first Butler hanger and Company "B" of our Battalion is erecting the second one. Our Battalion will erect the Blister Hangers, one of wood and two of prefabricated steel. |
6 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Today there were very few men working on the Airport in view of the fact that today is Sunday. The S-3 section had most of their men working so that the battalion would have everything set up in the morning. Most of the Battalion either went to church of slept till a late hour as today was a day of rest. A convoy was sent to Oxford for recreational purposes in the afternoon. The day was clear and cold, colder than we ever expected it to be here in this damp country. |
7 February 1944 |
Kingstson Bagpuize |
AIRPORT PROJECT
After a restful Sunday the men were eager to start off even though some think of it as a blue Monday. Co. A, Co. B, Co. C, H&S Co. Today the wind made it pretty rough for the S-3 and A.D.E. section working with the transit and level. It was a crisp cold day, but very windy. |
8 February 1944 |
Kingston Bagpuize |
Nothing new to add except that the same distribution of men and work as yesterday. The Airport is beginning to look like something now besides a mud hole. The mud has dried now except for a few fills. Both Butler Hangers are nearing completion and the Blister Hangers are rapidly taking shape. The new road (concrete is practically finished as far as pouring concrete goes. With good weather and a little luck and if we keep getting concrete fast enough it should be completed by the end of this week. The Battalion is also to start building Ronney Huts soon. ADE and S-3 sections are to start laying plans and surveying for them tomorrow. Quite a few of these Huts are to be built. They are pretty well scattered over the Airport. We have been fortunate lately as we have had good weather. |
9 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C. A.D.E. Section and S-3, Laying out foundation for Romney huts. H&S Co. On Staff and Service Functions. The weather today was cloudy and cold. At about 1510 we heard of a plane crash it was flashed over to me by phone and I immediately called H&S Co. to notify Capt. Doyle our medical officer. The story as I heard was that the plane was an Artillery Observation (Cub type) plane. The pilots name I could not get but one of our officers was also in the plane. Coming in to land the plane was caught in a downward draft and hit nose down. It immediately caught fire and men ran from all directions to help put the fire out and take the two men to safety. Lt. Col. Van Atta our C.O. was the first one to arrive at the scene of the Crash. Capt. Doyle said the pilot may not live whereas Lt. Helstrom may have a fractured jaw. The fine points of the crash are yet to be known. |
10 February 1944 |
Kingston Bagpuize |
Co. A, Half of the company working on now concrete Road. Remainder of company doing miscellaneous work on Runways. Co. B, Co. C, ADE & S-3 Section still on various jobs out on the airfield. H&S Co. On Staff and Service functions. The weather today was clear and cold. |
11 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C, ADE & S-3 Section: Still surveying on various jobs at the airport. H&S CO. On Staff and service functions. The weather today was clear and warm. Major Steele of the 204th Engrs paid the Bn a visit today. Col. Carter of First Army (Engineer) paid us a call and also inspected the camp site and the airport. |
12 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A, Co. B, Co. C, H&S Co. The weather today was clear and warm. |
13 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Due to the high priority this Airport Project has recently been given, the battalion has gone all out for work. A seven day week schedule has been put into force for everyone. The place is looking more and more like an airport everyday, the weather having been fairly decent for the past few days. The snow we had Thursday melted and left everything pretty wet for awhile, but now the mud is drying up and work is going full speed. The weather is still brisk but just right for good working conditions. The miscellaneous work being done on the runways at present is the result of rains and bad weather. The steel planking has to be lifted via crane or wrecker and sand sifted through in order to fill in the low spots which would be underwater if it should rain very hard. Constant traffic on the runways, while the ground was wet, has caused mud holes and slushes in the runway base. The Butler Hanger has been finished as far as erection is concerned . The canvas still has to be drawn and the floors sanded and graded. The Blister hanger is also near completion, canvas having to be drawn and floor to be graded. Due to the lack of wrenches of proper size a lot of bolts still need tightening. The central and southern end of the new cut-in road is completed, with the northern and needing filling and grading and concrete yet to be poured. Co A. Co B. Co C. H&S Co. |
Sections still surveying, using the Transit and Level constantly. |
14 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co A. Co B. Co C. H&S Co. The weather today has been very cloudy with the usual threats of rain. |
15 February 1944 |
Kingston Bagpuize |
AIRPORT PROJECT
Co. A Co. B. Co. C. H&S Co. The weather was cool and cloudy all day, with a light rain late in the evening. |
16 February 1944 |
Kingston Pagpuze |
AIRPORT PROJECT
Work at the airport is practically at a standstill today due to the very hard rains last night and nearly all day today. Rains such as this is really something to slow up the wheels of industry, and makes a lot more work before work can be started again. H&S Co. |
17 February 1944 |
Kingston Bagpuze |
The 342nd Engr Regt has raised the canvas on one of the
Butler Hangers making almost a complete job on one of the hangers.
The men on our Butler should be raising their canvas tomorrow,
weather permitting. The rains of yesterday has raised havoc with the
runways once more, following is the disposition of the company:
Co. A. Co. B. Co. C. H&S Co. The weather is somewhat clearer but quite cold. |
18 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT
Co. A. Co. B. Co. C. H&S Co. The weather is quite clear but very cold. |
19 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT
Co. A. Co B. Co. C. H&S Co. The weather is slightly cloudy with the sun shining every now and then. |
20 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT
Co. A. Co. B. Co. C. H&S Co. |
21 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
Co A. First Platoon still on the new road at the Northern end of the new airport, doing grading and pouring of the cement. The Second Platoon is out at the the new camp site getting ready for the troops to move in, erecting tents, clearing and etc. The Third Platoon is busy on the Romney Huts on the airport they are just erecting the framework for one new hut after having laid the foundation. Co. B. Co. C. H&S Co. The weather is fairly clear but very cold. |
22 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
Co. A. The first and Second Platoons are busy on the new road and also the new Romney Huts. The road is almost completed. The new hut that was just started yesterday is shaping up very rapidly. The Third platoon is still located out at the new camp site and will stay there until joined by the rest of the company. Co. B. Co C. H&S Co. The weather is beautiful this AM Clear and sunny. |
23 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
The project is very near to completion with both the Butler
Hangers completed and the Three Blister Hangers very nearly
finished. The Concrete road is all but finished, with all the
concrete poured now comes removal of the forms and the final
grading. All companies are working together to finish up this job by
the end of the month.
The weather was a bit cloudy this morning but by afternoon the sun came out and it turned fairly warm. |
24 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
All companies are very busy today with parts of each company out
at the new area. In the new area B Co is running the mess and doing
a fine job of it by all reports.
The Airport is gradually shaping up to what it should be, with some pierced planking yet to be laid on the hard standings and the taxiways, there grading yet to be done on the new road and a few Romney huts to be built which is to be used as supply huts for the air forcow. The runways and Hangers are all finished. The weather is clear and very cold. |
25 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
The work on the airport is coming along in fine shape with all
projects coming near to completion. The grading on the new road is
nearly finished and the Romney Huts are coming along in fine shape,
begins to look like the job will be finished by the end of the month
as far as the 150th is concerned.
The new area is practically ready to receive its additional personnel and the S-3 section has a drawing of the area very nearly completed, a fine piece of work, worked out to the exact scale. The weather today has been fairly warm with clouds and light mists at night. |
26 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
Only a very little work left for the 150th is
concerned. The work on the Blister Hangers is very nearly done with
only a little grading left to do. The concrete road will not be
entirely completed by this unit, the work will be taken over by the
Air Ministry and finished with civilian workmanship.
There is a lot of work left to be done in the new area at Clifton Heath. More than one would realize. The weather is fairly cold with a light snow. |
27 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
Today being Sunday there is no work, the first rest day in nearly
a month. Most of the men have gone into Oxford on pass.
The weather quite warm and a little cloudy. |
28 February 1944 |
Kingston Bagpuze |
AIRPORT PROJECT |
Very few men and working on the airport due to the anticipated
move, most men are packing equipment and doing general police duty.
There is nearly two platoons still working on the grading around the
Blister Hangers.
The weather is quite cool and cloudy. |